Method Statement for Painting Works

Sharing is Caring:
85 / 100

After completion of preparatory works such as the installation of block, plaster preparation, plaster works, and then the painting works will then be carried out. In this article will show the procedure on how painting activities will be done.

Now here is the method statement for painting works.

1. Title

Method Statement for Painting Works

2. Purpose and scope

The purpose of this method statement for painting works is to describe the measures and ways of proper application of paint at control tower. Works shall be carried out in compliance with the drawings, project specifications, and materials.

3. Work procedure

3.1 Mock-up

  • Mockup sample would be made for selection and approval of the Engineer prior to commencement of the works.

3.2 Preparation

3.2.1 Hardware materials that are already fixed and not to be painted shall be removed. Removal if not possible, shall be covered/protected appropriately before surface preparation and painting will commence.

3.2.2 Clean and prepare concrete or cement plaster surfaces to be painted. Efflorescence, chalk, dust, dirt, grease, and oils shall be removed.

Read also:  7 Types of Concrete Block Used in Building Construction

3.2.3 The surface of the area to be painted would be prepared by removing loose particles, blemishes, and deleterious materials by way of sanding.

 

methodstatementforpaintingworks

 

3. Paint Application

3.1 The paint system would be emulsion paint for internal but to be approved by the Engineer. The surface to be painted when prepared one coat of paint to be applied as primer. Curing would be made by drying until 4 hours is attained prior to the succeeding coat to be applied.

3.2 Two coats of Stucco would be applied after the primer has reached its curing period. But each coat shall have an interval time of 4 hours for curing. Before the application of the second coat stucco sanding would be done for cleaning and removing splattered, blemishes, and stains on the painted surface.

3.3 Then two coats of final paint would be applied as per the approved RAL color.

3.4 For working at height, fixed and movable scaffolding would be erected as per area requirements. Scaffolding when erected shall be inspected with the Safety officer prior to usage. Operatives will be inductive before working at the site. Pre-start meeting would be conducted before the start of painting activities and toolbox meetings would be regularly conducted by safety officers for all concerned operatives.

Read also:  Method Statement for Dewatering

3.4 Inspection Request to be submitted for checking and approval of the Engineer.

4. Safety

4.1 All works shall comply with safety procedures or instructions set out in the project safety plan and Municipality rules and regulations.

4.2 Basic PPE to be worn by all staff or laborers.

4.3 All operatives involved in this work shall be inducted before entering the site.

4.4 Toolbox talk shall be conducted regularly.

5. Equipments and tools

5.1 Wheel borrow

5.2 Drip tray

5.3 Drill machine

5.4 Pail

5.5 Sandpaper

5.6 Rug cloth

6. Materials and references

6.1 Approved paints

6.2 Scope of works or specification

6.3 Approved drawing

Related Article:

  1. Method Statement for Painting Works for External Concrete Beam
  2. Method Statement for Epoxy Risen Floor Coating
  3. Method Statement for Chasing New Ceiling for New Location of Light Points and Junction Box
Did you follow the above method statement for painting works? If you do, please comment down your experience and suggestions.

Please like our Facebook page and you may write down your thoughts on the comment box below.

Read also:  Method Statement for Epoxy Risen Floor Coating System

Painting Tips no. 1

Make sure that the method statement is approved before starting painting work.

Painting Tips no. 2

Ensure that the material for painting is approved via material submittal or material approval report.

Painting Tips no. 3

The surface preparation must be done and should be checked by the Engineer before starting paint application.

Painting Tips no. 4

For Safety, ensure that the operatives involved in the painting works are inducted. PPE shall be worn at all times during painting activity.